By Glynis Crawford Smith
The Highlander
Construction on the new Marble Falls Public Safety Center (PSC) is set to begin next month, following action by the city council Tuesday, Oct. 18, to approve a construction contract.
A contract was approved with STR Constructors, LTD, for $3,482,635 for the new center to house the Marble Falls Police Department and Municipal Court on Avenue N.
“We had six builders submit sealed competitive bids, one of the qualified being the low bidder,” said City Manager Mike Hodge. “The official submitted total $3,725,000 and we were able to negotiate that down.”
Jettisoned from the initial plans prepared by architects for the project, R. Gill Architects of Horseshoe Bay, were such items as copper pipe in favor of synthetic plumbing materials and alternate bids for a sally port (controlled entrance) and some covered parking.